our Projects

  • 01/

    Bear park Project

    The Bear Park Project was completed in 1984. The designed to hold 4000 acre feet of water during high runoff events, reducing flood damages on the Sand Hill and Red River.
  • 02/

    V. Olson Dam

    The Verdell Olson Dam began with the construction of a detention dam in the outlet channel from a 50 acre basin. The dam eliminated damages caused by extremely high flows each spring.
  • 04/

    Winger Dam

    The proposed Winger Dam was designed to hold 12,000 acre feet creating a lake with 6,000 acrea feet of possible flood storage. After years of effort and expense, the project died due to the inability to obtain proper permiting from the US Army Corp and MN DNR.
  • 08/

    Ogaard Impoundment

    The project was meant to complement the Winger Dam and provide mitigation for the dam. This project died when the Winger Dam was denied permitting.
  • 09/

    River Clean up

    To complement the district's missions statement, the district supported all efforts to clean our local river. Tires, mattresses, garbage, carcuses, and appliances were just a few things found and removed from our river.
  • 09/A

    River Stabilization

    The Sand Hill River Watershed district installed riprap at four erosion protection areas along the Sand Hill River. Three of these areas are located in the vicinity of the city of Fertile in sections 20 and 29 of Garfield Township. The fourth site is located in the NW 1/4 of sect(ion 28, Liberty Township.
  • 10/

    West Mill

    The City of Fertile petitioned the Sand Hill River Watershed District with a proposed recreational lake west of Fertile at the site of a feed mill that failed in 1950. The project died due to a lack of funding and MN DNR permitting restraints.
  • 15/

    Ring Dikes

    Farmstead Ring Dikes
    City Ring Dikes
    The Sand Hill River Watershed District has assisted in the construction of many ring dike projects, mostly on the west end of the district. The latest project is a ring dike around the City of Climax. The district is waiting funding for a ring dike around the City of Nielsville
  • 16/

    Kurass Lake

    The Watershed District assisted Garfield Township in 1998 with control structure to lower the lake level of Kurass Lake and establish an ordinary high water level.
  • 18/

    Vesledahl Wetland Banking

    Multiple agencies planned to develop and restore areas of wetlands that will serve as a "bank" for wetland "credits" to be used to offset damages done to other wetlands for road construction projects.
  • 19/

    Union Lake Erosion Control

    The district discovers a a workable solution for solving the erosion that was occurring at the site in section 31 of Knute Township, Polk County, Minnesota.
  • 21/

    Fish Passage

    Since the early 2000's the Sand Hill River Watershed District has collaborated with partnering agencies to restore the Sand Hill River and make it a viable fishery once again.
  • 22/

    Section 23/Russia Boundary

    Collaboration between the Red Lake Watershed District and the Sand Hill River Waterhsed District solves flooding for local landwoners.
  • 23/

    Section 23/Russia Boundary

    Collaboration between the Red Lake Watershed District and the Sand Hill River Waterhsed District solves flooding for local landwoners.
  • 28/

    King Township- Hopke Diversion

    The district cost shares with King Township to maintain the district's policy to manage water through a grass waterway vs. crossing farm fields.
  • 29/

    Rock riffles

    The Sand Hill River Watershed District collaborated with many partners to minimize future head cutting along the Sand Hill channel and reduce to occurrence of bank sluffing.
  • 30/

    Jerde/Taylor Erosion control

    The District helps landowners implement erosion control measures in Section 13 of Liberty Township.

 

Rock riffles

Project # 29

PROJECT PHOTOS:

Click here for photos


PROJECT SETTING:Hearld_news

Historically, the Sand Hill River near the community of Beltrami, MN had limited capacityand resulted in frequent overland flooding throughout the region. In an effort to reduce overland flooding, portions of the Sand Hill River were straightened and channelized in the 1950s as part of a US Army Corps of Engineers (USACE) flood control project. The channelization project was completed in portions of Hubbard Township, Scandia Township, Reis Township, and Liberty Township. This area is characterized by moderate to steep landscape slopes along the Lake Agassiz Beach Ridge in the east, with slopes flattening further west. The USACE channelization project provides an outlet for primarily agricultural lands within the Sand Hill River Watershed.

NEED FOR ACTION:

Channelization of the Sand Hill River by the USACE resulted in a steeper channel slope by removing meanders and replacing with a less sinuous channel. The project also resulted in less floodplain storage, with more flow being contained within the constructed channel. In an attempt to mitigate the potential for channel erosion resulting the steep gradeline and reduced floodplain storage, the USACE channelization project also included the installation of four concrete drop structures. These structures allow for a controlled drop for flows in the channel to reduce velocities in open ditch portions of the channel. While these structures assisted in stabilizing the channel, a steep gradeline was still left between each drop structure, and downstream of the western most drop structure. This has resulted in much of the constructed channel experiencing significant erosion since construction of the USACE project. One area of significant channel erosion the portion of the channelization project located east of Beltrami, MN. Through this region, approximate 5-7 feet of head cutting along the channel has occurred. This head cutting has led to bank failure at many locations, with sluffs encroaching on adjacent private land. Over time this bank sluffing has resulted in formation of a vegetated floodplain within the eroded channel. However, without stabilization of the developing stream thalweg it’s likely that the channel will continue to erode at an unnatural rate. The current channel profile and cross sections as compared to the USACE project design channel profile and cross sections are presented in the attached Construction Plans.

PROPOSED PROJECT:

In order to stabilize head cutting along the Sand Hill River east of Beltrami, MN, installation of 16 rock riffles are proposed along the Sand Hill River east of Beltrami, MN. These locations are illustrated in the attached Construction Plans. In total, these 16 rock riffles will provide a controlled drop that will mitigate 21 vertical feet of fall from the existing Sand Hill channel. Each riffle is designed to provide approximately 0.1 feet of backwater on the next upstream riffle. This design configuration will minimize future head cutting along the Sand Hill channel and reduce to occurrence of bank sluffing currently experienced.

A secondary objective of the rock riffles is to ensure they do not become a barrier to fish passage along the Sand Hill River. The USACE, working in collaboration with the MN Department of Natural Resources (MN DNR) and the SHRWD, are in the process of modifying the four (4) concrete drop structures that were installed as part of the USACE’s channelization work in the 1950s. This process involves retrofitting the concrete drop structures with rock riprap at a flat enough slope to allow fish passage upstream across each structure. The rock riffles proposed for grade stabilization in the Sand Hill River are also designed to ensure upstream fish passage across each. The proposed slope of each rock riffle varies from 0.03% for riffles greater than one foot of vertical fall, to 0.04% for riffles less than one foot of vertical fall. Vertical fall is when measured to the crest of the next downstream rock riffle. Additionally, for rock riffles greater than one foot of vertical fall, rock arches will be installed to provide necessary resting areas for fish as the climb the riffle. These rock arches will be installed at 26 foot intervals along the riffle, starting 26’ downstream of the riffle crest. The arches will be constructed of large boulders (36 – 72 inch diameter; 48 inch typical) that will be set to leave one foot exposed above the rock riffle.

Each rock riffle was designed to fully contain the bank full flow event, or approximately the 1.5 year recurrence flow rate. In order to convey this flow rate, each riffle will have a maximum depth of six (6) feet, a bottom width of 22 feet, and a top width 46 feet. Based on field survey collected by the MN DNR in 2015, this appears to match the existing channel and ties in well with the developing floodplain that has resulted from bank sluffing. The upper layer of rock riprap will be two (2) feet thick and will be constructed of MN Department of Transportation (MN DOT) Class III Riprap. This gradation consists of round field stone of 18 inch maximum diameter. This size of rock riprap will withstand velocities expected within the Sand Hill channel. Some channel excavation will be required where the existing channel is less than two (2) from the finish grade of the proposed rock riffles. Excavated material will be placed along the upstream end of the rock riffle in the Sand Hill River channel to assist in plugging voids within the placed rock riprap. In areas where the existing channel is greater than two (2) feet lower than the finish grade of the rock riffles, MN DOT Class I Riprap will be used to provide fill. The gradation of MN DOT Class I Riprap consists of round field stone with a maximum six (6) inch diameter. More details on the rock riffle geometry is available in the attached Construction Plans.

HYDRAULIC IMPACTS TO THE USACE CHANNELIZATION PROJECT:

The Sand Hill River Grade Stabilization Project will have no adverse impacts to the hydraulic capacityRock Riffles of the USACE Channelization Project. The layout of the rock riffles is below the design gradeline and cross sections of the USACE Channelization Project. The riffle crest elevation, existing channel gradeline, and the USACE project design gradeline are presented in the attached Construction Plans. Additionally, the existing cross sections, rock riffle cross sections, and USACE project design cross sections are also available in the attached Construction Plans. Because all work is being done below the USACE design finish grade for the constructed channel, the design channel capacity for the USACE Channelization Project will remain unaffected.

PERMITTING:

The SHRWD worked with agencies to acquire the proper permits for the project. These permits include:

  • US Army Corps of Engineers 404 Permit

  • US Army Corps of Engineers 408 Permit

  • Minnesota Department of Natural Resources Public Waters Permit

  • Minnesota Wetland Conservation Act

FUNDING:

The primary funding source for the Proposed Project is Minnesota’s Clean Water Land and Legacy Amendment. A portion of funds generated from this Amendment are administered through the MN Board of Water and Soil Resources (BWSR) Clean Water Fund grant program. The West Polk Soil and Water Conservation District (SWCD) was successful in attaining a $475,000 grant from the BWSR Clean Water Fund for the Sand Hill River Grade Stabilization Project. These funds require a 25% minimum match of awarded grant dollars, which is being provided by the Sand Hill River Watershed District, and a $100,000 Enbridge Ecofootprint Grant

CONSTRUCTION TIMELINE

The SHRWD Project No. 29, Sand Hill River Grade Stabilization Project, was completed in the fall of 2016.

our Partners

  • LEGACY LOGO

    On November 4th 2008, Minnesota voters approved the Clean Water, Land and Legacy Amendment to the state constitution. This amendment passed with 56% of the vote. Click here

  • bwsr lOGO

    BWSR is the state soil and water conservation agency, and it administers programs that prevent sediment and nutrients from entering our lakes, rivers, and streams; enhance fish and wildlife habitat; and protect wetlands.

  • WPSWCD LOGO

    The three-year, $3 million grant program began in 2015 to support a range of environmental projects – from improving water quality to limiting impact on wildlife and migratory birds to fostering education and overall stewardship. Visit Enbridge to find out more.




  • WPSWCD LOGO

    The Sand Hill River Watershed District and the wEST Polk SWCD in McIntosh, MN collaborate on many of the same goals in initiatives within the district.

  • HE LOGO
    Houston Engineering has been the Sand Hill River Waterhsed District's engineering firm since the district's originiation. The district's Engineer is Zach Herrmann.