our Projects

  • 01/

    Bear park Project

    The Bear Park Project was completed in 1984. The designed to hold 4000 acre feet of water during high runoff events, reducing flood damages on the Sand Hill and Red River.
  • 02/

    V. Olson Dam

    The Verdell Olson Dam began with the construction of a detention dam in the outlet channel from a 50 acre basin. The dam eliminated damages caused by extremely high flows each spring.
  • 04/

    Winger Dam

    The proposed Winger Dam was designed to hold 12,000 acre feet creating a lake with 6,000 acrea feet of possible flood storage. After years of effort and expense, the project died due to the inability to obtain proper permiting from the US Army Corp and MN DNR.
  • 08/

    Ogaard Impoundment

    The project was meant to complement the Winger Dam and provide mitigation for the dam. This project died when the Winger Dam was denied permitting.
  • 09/

    River Clean up

    To complement the district's missions statement, the district supported all efforts to clean our local river. Tires, mattresses, garbage, carcuses, and appliances were just a few things found and removed from our river.
  • 09/A

    River Stabilization

    The Sand Hill River Watershed district installed riprap at four erosion protection areas along the Sand Hill River. Three of these areas are located in the vicinity of the city of Fertile in sections 20 and 29 of Garfield Township. The fourth site is located in the NW 1/4 of sect(ion 28, Liberty Township.
  • 10/

    West Mill

    The City of Fertile petitioned the Sand Hill River Watershed District with a proposed recreational lake west of Fertile at the site of a feed mill that failed in 1950. The project died due to a lack of funding and MN DNR permitting restraints.
  • 15/

    Ring Dikes

    Farmstead Ring Dikes
    City Ring Dikes
    The Sand Hill River Watershed District has assisted in the construction of many ring dike projects, mostly on the west end of the district. The latest project is a ring dike around the City of Climax. The district is waiting funding for a ring dike around the City of Nielsville
  • 16/

    Kurass Lake

    The Watershed District assisted Garfield Township in 1998 with control structure to lower the lake level of Kurass Lake and establish an ordinary high water level.
  • 18/

    Vesledahl Wetland Banking

    Multiple agencies planned to develop and restore areas of wetlands that will serve as a "bank" for wetland "credits" to be used to offset damages done to other wetlands for road construction projects.
  • 19/

    Union Lake Erosion Control

    The district discovers a a workable solution for solving the erosion that was occurring at the site in section 31 of Knute Township, Polk County, Minnesota.
  • 21/

    Fish Passage

    Since the early 2000's the Sand Hill River Watershed District has collaborated with partnering agencies to restore the Sand Hill River and make it a viable fishery once again.
  • 22/

    Section 23/Russia Boundary

    Collaboration between the Red Lake Watershed District and the Sand Hill River Waterhsed District solves flooding for local landwoners.
  • 23/

    Section 23/Russia Boundary

    Collaboration between the Red Lake Watershed District and the Sand Hill River Waterhsed District solves flooding for local landwoners.
  • 28/

    King Township- Hopke Diversion

    The district cost shares with King Township to maintain the district's policy to manage water through a grass waterway vs. crossing farm fields.
  • 29/

    Rock riffles

    The Sand Hill River Watershed District collaborated with many partners to minimize future head cutting along the Sand Hill channel and reduce to occurrence of bank sluffing.
  • 30/

    Jerde/Taylor Erosion control

    The District helps landowners implement erosion control measures in Section 13 of Liberty Township.

 

Bear Park

Project # 1


Bear Park PhotosProject #1 involved the replacement of an existing bridge on a Bear Park Township road in Norman County with a flood detention structure. This structure was constructed with extensive coordination with the Norman County Highway Department, Minnesota Department of Transportation, and the Sand Hill River Watershed District. In 1977, the Board authorized preliminary studies on this project and applied to the Lower Red River Waterhsed Management Board for funds. On September 18, 1978, the Board of Managers officially instituted this project by a unanimous resolution of the Board of Managers.

The replacement flood detention structure serves the dual purpose of providing a safer and more adequate road crossing across the Sand Hill River, as well as serving as a flood detention structure. The proposed strucutre is located on the township road between Sections 11 and 12 of Bear Park Township (T146N, R43W), Norman County. The structure provides approximately 3800 acre-feet of storage with no permanent pool. The impoundemnt area stretches upstream approximately 4.5 miles to the Polk County and Mahnomen County line.

The preliminary engineering report for this project was completed and submitted to the Board on March 15, 1979. On March 19, 1979, copies of the preliminary engineering report were sent to the Water Resources Board and Department of Natural Resources for their review. Permit applications were submitted to the DNR and the U.S. Army Corps of Engineers on March 20, 1979 and March 23, 2979, respectfully.

A public hearing on the Engineer's and Viewer's Report was held July 10, 1979. On July 17, 1979, the Board of Managers ordered their attorney to go ahead with condemnation on the lands not acquired by easement. The Water Resources Board's comments were received July 26, 1979.

An agreement between the Lower Red River Water Management Baord and the D.N.R. of the State of Minnesota was made October 2, 1979. This agreement says that 50% of the project costs, not to exceed $180,500.00 will be paid by the State through the Legislative Committeee on Minnesota Resources.

The validated copy of the Department of the Army, Corps of Engineers Permit was received January 22, 1980.

All the land needed to construct this project was not readily obtainable. A petition for condemnation was filed on May 27, 1980. The preliminary hearing took place at 2 PM, July 2, 1980 in Mahnomen, MN and the land was available to the Board later in 1980.

On October 21 and November 18, 1980, the additional information required by the Dam Safety Section of the Minnesota Department of Natural Resources was submitted. On November 26, 1980, the DNR permit was received.

The bid opening was held on October 29, 1980 and the low bidder was Drewes Construction, Co. of Detroit Lakes, MN with a total base bid of $183,132.55. The Watershed District entered into a contract with the low bidder on December 15, 1980.

Construction started on June 10, 1981 and was virtually completed in October 1981, with exception of seeding and some minor clean-up work. This proejct was completed and accepted by the Board of Managers in July 1982 with a construction cost of $202,905.85.

In 1984, Drewes Construction completed the construction of an access road on a parcel of land within the reservoir area.

In 2013, the district began alternative analysis for improvements that would assist in reducing the Sand Hill Watershed’s contributions to flooding on the main stem of the Red River of the North. The project drainage area lies in the “middle” region of the Red River Basin, as defined by the Red River Flood Damage Reduction Work Group. The runoff produced from this area contributes to the peak on the main stem of the Red River, and a strategic method of reducing the impact of these areas is to store the water on the landscape.  Project benefits include providing gated storage for up to 5,600 acre-ft, enhance benefits of the existing project for lands adjacent to the Sand Hill River and Red River, and the project is part of the Red River Basin Commission’s Flood Damage Reduction Strategy.

Project Maintenance

Google_Earth_Image_of_Bear_Park_ProjectScouting for beaver is done regularily to remove impediments to the river in relation to the structure.

2017 Maintenance

In the spring 2017, this district found 4 beaver lodges, and 2 beaver dams in the stretch relating to the Bear Park structure.To see imagry of our spring findings, Click Here. You mut have Google Earth downloaded to view the imagry. Spring 2017 drone footage can be found here.

In the fall of 2017 the district found multiple beaver lodges and and expanded their search to include downstream of the structure. To see imagry of our fall findings, Click Here. The fall 2017 drone footage can be found is shown at the top of this page and can also be found here.

2018 Maintenance

In the spring 2018, the route inspected by kayak was from US Hwy 59 south of Winger to the Harstad bridge just downstream of Rindal for purposes of scouting this reach for beaver dams. This is a total river distance of approx. 17.4 river miles. To see imagry of our spring findings, Click Here. You mut have Google Earth downloaded to view the imagry. A complete written report can be found here.

2019 Maintenance

In the spring 2019, the route inspected by kayak was from Mahnomen CoRd 107 southwest of Winger to Rindal for purposes of scouting this reach for beaver dams. This is a total river distance of approx. 11.7 river miles. To see imagry of our spring findings, Click Here. You mut have Google Earth downloaded to view the imagry. A complete written report can be found here. During the spring of 2019, over 40 beaver were trapped in the area. Precipitation was high in 2019, leaving the district unable to effectively remove under water dams.

In addition to proactive maintenance east of Rindahl, the district received a clean water fund grant for river clean up efforts. A crew of AmeriCorps members ages 18 to 25, based in Fergus Falls, removed fallen trees and cleared areas for recreation along a 6.3 mile stretch of the Sand Hill River between Rundahl and Polk County Highway 1. The crew removed garbage, trees, structures making a safe and clean passage through the waterway. The project was supported through funding from the Board of Water and Soil Resources (BWSR) and the Corporation for National & Community Service (CNCS).