our Projects

  • 01/

    Bear park Project

    The Bear Park Project was completed in 1984. The designed to hold 4000 acre feet of water during high runoff events, reducing flood damages on the Sand Hill and Red River.
  • 02/

    V. Olson Dam

    The Verdell Olson Dam began with the construction of a detention dam in the outlet channel from a 50 acre basin. The dam eliminated damages caused by extremely high flows each spring.
  • 04/

    Winger Dam

    The proposed Winger Dam was designed to hold 12,000 acre feet creating a lake with 6,000 acrea feet of possible flood storage. After years of effort and expense, the project died due to the inability to obtain proper permiting from the US Army Corp and MN DNR.
  • 08/

    Ogaard Impoundment

    The project was meant to complement the Winger Dam and provide mitigation for the dam. This project died when the Winger Dam was denied permitting.
  • 09/

    River Clean up

    To complement the district's missions statement, the district supported all efforts to clean our local river. Tires, mattresses, garbage, carcuses, and appliances were just a few things found and removed from our river.
  • 09/A

    River Stabilization

    The Sand Hill River Watershed district installed riprap at four erosion protection areas along the Sand Hill River. Three of these areas are located in the vicinity of the city of Fertile in sections 20 and 29 of Garfield Township. The fourth site is located in the NW 1/4 of sect(ion 28, Liberty Township.
  • 10/

    West Mill

    The City of Fertile petitioned the Sand Hill River Watershed District with a proposed recreational lake west of Fertile at the site of a feed mill that failed in 1950. The project died due to a lack of funding and MN DNR permitting restraints.
  • 15/

    Ring Dikes

    Farmstead Ring Dikes
    City Ring Dikes
    The Sand Hill River Watershed District has assisted in the construction of many ring dike projects, mostly on the west end of the district. The latest project is a ring dike around the City of Climax. The district is waiting funding for a ring dike around the City of Nielsville
  • 16/

    Kurass Lake

    The Watershed District assisted Garfield Township in 1998 with control structure to lower the lake level of Kurass Lake and establish an ordinary high water level.
  • 18/

    Vesledahl Wetland Banking

    Multiple agencies planned to develop and restore areas of wetlands that will serve as a "bank" for wetland "credits" to be used to offset damages done to other wetlands for road construction projects.
  • 19/

    Union Lake Erosion Control

    The district discovers a a workable solution for solving the erosion that was occurring at the site in section 31 of Knute Township, Polk County, Minnesota.
  • 21/

    Fish Passage

    Since the early 2000's the Sand Hill River Watershed District has collaborated with partnering agencies to restore the Sand Hill River and make it a viable fishery once again.
  • 22/

    Section 23/Russia Boundary

    Collaboration between the Red Lake Watershed District and the Sand Hill River Waterhsed District solves flooding for local landwoners.
  • 23/

    Section 23/Russia Boundary

    Collaboration between the Red Lake Watershed District and the Sand Hill River Waterhsed District solves flooding for local landwoners.
  • 28/

    King Township- Hopke Diversion

    The district cost shares with King Township to maintain the district's policy to manage water through a grass waterway vs. crossing farm fields.
  • 29/

    Rock riffles

    The Sand Hill River Watershed District collaborated with many partners to minimize future head cutting along the Sand Hill channel and reduce to occurrence of bank sluffing.
  • 30/

    Jerde/Taylor Erosion control

    The District helps landowners implement erosion control measures in Section 13 of Liberty Township.

 

Bear Park

Project # 1


Bear Park PhotosProject Overview

The Bear Park Project is a flood detention structure located on the Sand Hill River in Bear Park Township, Norman County, Minnesota. Originally constructed to replace an aging bridge crossing, the project was designed to provide both a safe roadway crossing and flood damage reduction benefits for the watershed.

Completed in 1982, the structure provides approximately 3,800 acre-feet of temporary floodwater storage and has helped reduce flood damages along the Sand Hill River and throughout the Red River Basin. The impoundment area extends approximately 4.5 miles upstream to the Polk and Mahnomen County line.

Purpose and benefits

The Bear Park Project was developed to help address flooding within the Sand Hill River Watershed by temporarily storing runoff during periods of high flow. By reducing peak flows, the project provides benefits to downstream landowners, communities, infrastructure, and agricultural lands.

Project benefits include:

  • Reduction of peak flood flows during major runoff events
  • Protection of agricultural lands and infrastructure
  • Support of regional flood damage reduction efforts
  • Temporary floodwater storage without a permanent pool
  • Long-term watershed management benefits

Project funding

The Bear Park Project was made possible through a partnership between local and state government entities committed to reducing flood damages within the Sand Hill River Watershed. On October 2, 1979, the Lower Red River Water Management Board and the Minnesota Department of Natural Resources entered into a funding agreement providing assistance through the Legislative Commission on Minnesota Resources (LCMR).

Under the agreement, the State of Minnesota committed to funding 50 percent of eligible project costs, not to exceed $180,500. This investment helped make construction of the project possible while reducing the financial burden on local taxpayers.

The partnership reflected a shared recognition that flood damage reduction projects provide benefits extending beyond local boundaries. More than four decades later, the Bear Park Project continues to provide flood storage and downstream flood protection benefits, demonstrating the long-term value of investments in watershed infrastructure.

Project Timeline

Date Milestone
1977 The Board of Managers authorized preliminary investigations to evaluate replacing the existing bridge crossing with a structure capable of providing floodwater storage benefits.
September 13, 1978 The Bear Park Project was officially established by the Sand Hill River Watershed District.
March 15, 1979 The preliminary engineering report was completed and submitted to the Board of Managers.
March 19, 1979 Copies of the preliminary engineering report were submitted to the Minnesota Water Resources Board and Minnesota Department of Natural Resources for review.
March 20, 1979 Permit application submitted to the Minnesota Department of Natural Resources.
March 23, 1979 Permit application submitted to the U.S. Army Corps of Engineers.
July 10, 1979 Public hearing held on the Engineer's Report and Viewer's Report.
July 17, 1979 The Board of Managers directed legal counsel to proceed with condemnation proceedings for lands not acquired through easement agreements.
July 26, 1979 Comments from the Minnesota Water Resources Board were received.
October 2, 1979 Funding agreement executed between the Lower Red River Water Management Board and the Minnesota Department of Natural Resources. Through the Legislative Commission on Minnesota Resources (LCMR), the State agreed to fund 50 percent of project costs, not to exceed $180,500.
January 22, 1980 Validated permit received from the U.S. Army Corps of Engineers.
May 27, 1980 Petition for condemnation filed to acquire remaining lands needed for project construction.
July 2, 1980 Preliminary condemnation hearing held in Mahnomen, Minnesota. The required lands were subsequently made available to the Board later in 1980.
October 21, 1980 Additional information requested by the Minnesota DNR Dam Safety Section was submitted.
October 29, 1980 Bid opening conducted. Drewes Construction Company of Detroit Lakes submitted the low base bid of $183,132.55.
November 18, 1980 Additional information requested by the Minnesota DNR Dam Safety Section was submitted.
November 26, 1980 Minnesota Department of Natural Resources permit received.
December 15, 1980 Construction contract awarded to Drewes Construction Company of Detroit Lakes, Minnesota.
June 10, 1981 Construction of the Bear Park Project began.
October 1981 Major construction activities were substantially completed, with only seeding and minor cleanup remaining.
July 1982 Project completed and officially accepted by the Board of Managers. Final construction cost was $202,905.85.
1984 Drewes Construction completed an access road within the reservoir area.
2013 The District initiated an alternatives analysis to identify opportunities for additional floodwater storage and flood damage reduction. Potential improvements included up to 5,600 acre-feet of gated storage, enhanced benefits for lands adjacent to the Sand Hill River and Red River, and support of the Red River Basin Commission's Flood Damage Reduction Strategy.
2026 The Board of Managers established the Bear Park Project Team to explore opportunities for additional flood damage reduction, water quality improvements, and other watershed benefits associated with the Bear Park area.
```

Project Maintenance

Google_Earth_Image_of_Bear_Park_ProjectThe Sand Hill River Watershed District conducts regular inspections and maintenance activities to ensure the project continues to function as intended.

Maintenance efforts have included:

  • Structure inspections and maintenance
  • Beaver dam and lodge monitoring and removal
  • Drone and field surveys
  • River corridor inspections
  • River cleanup activities

These efforts help protect the public investment in flood damage reduction infrastructure and maintain the project's long-term effectiveness.

Looking ahead

The Bear Park Project continues to play an important role in reducing flood damages within the watershed. As watershed needs evolve, the Sand Hill River Watershed District continues to evaluate opportunities that could build upon the success of existing infrastructure.

In 2026, the Board of Managers established a Bear Park Project Team to explore opportunities for additional flood damage reduction, water quality improvements, and other watershed benefits associated with the Bear Park area. The team provides a forum for stakeholder input and helps identify concepts that may warrant future evaluation.

The formation of the Project Team does not commit the District to any specific project. Rather, it allows local stakeholders, landowners, and agency representatives to collaboratively discuss ideas, evaluate potential benefits and impacts, and determine whether additional study is appropriate.

For information on current discussions and Project Team activities, visit the Bear Park Project Team page.

Archived Documents

Map of board approved jurisdictional area